Our own team, trusted specialists

HV jointing Making off 11 kV terminations into a ring main unit, by UK Power Connections’ jointers.

The ring main unit An RMU and packaged transformer set in a new substation compound, glands made off and earthed before anything is energised.

Transformer terminations Heat-shrink boots over the HV terminations on a new ground-mounted transformer — phase-marked, torqued and tested before the covers go on.

Set, glanded, ready The finished HV side of a new substation: cable dressed up through the gland plate and terminated to the bushings, in a compound barely wider than the unit.

Bedded and marked Sand-bedded cable with warning tape over the full run — the unglamorous detail that stops a spade finding it in five years.

Street works, managed A cable route through a live high street: winch set, trench boarded, footway kept open and reinstated to specification.

Craned into a tight compound Half a tonne of transformer landed behind a housing scheme, terminated and labelled where a lorry could barely reach.